Transmission Company of Nigeria (TCN) was incorporated in November 2005. TCN emerged from the defunct National Electric Power Authority (NEPA) as a product of the merger of the Transmission and Operations sectors on April 1, 2004.
Being one of the 18 unbundled Business Units under the Power Holding Company of Nigeria (PHCN), the company was issued a transmission License on 1st July, 2006. TCN licensed activities include: electricity transmission, system operation and electricity trading which is ring fenced.
Transmission Service Provider of Nigeria (TSPN)
Nigeria Electricity System Operator (NESO)
Disco Load Summary
Download 7th - 14th March, 2017... (View More)
View Grid Performance
Advert Documents
Download Advert for PQ
Expression of Interest: Update of the ECOWAS Revised Master Plan for the Generation and Transmission of Electrical Energy (2012 - 2025)
Procurement Notice
Download Issued Specific Procurement Notice
Communique
16th Monthly Meeting Communique (View Pictures in the Photo Gallery)
Regional Contacts Nationwide
The Permanent Secretary, Power, Ministry of Power, Works and Housing, Mr. Louis Edozien, has applauded the Transmission Company of Nigeria (TCN), for striving to remain well ahead of generation with the widespread ongoing nation - wide expansion of its network.
The Transmission Company of Nigeria (TCN) has said that it has successfully restored electricity supply to Birinin Gwari and Yauri in Kaduna and Kebbi States respectively. Power supply was restored at about 5:10pm on Monday, 24th July, 2017, 11days after the collapse of tower No 183 on Thursday, 13th July, 2017.
The Transmission Company of Nigeria has again increased transformer capacity in its Ajah substation with an additional 60MVA 132/33kV power transformer, which was successfully refurbished, installed and commissioned into service on July 11th, 2017, bringing the stations’ transformer capacity at 132kV level to 220MVA.
The Federal Government has commissioned the 2x60MVA, 132/33kV transmission substation, Kukwaba, Abuja, built by the Transmission Company of Nigeria (TCN), as part of efforts to improve power supply situation within the Federal Capital Territory (FCT).
The management of the Transmission Company of Nigeria (TCN) says it has carried out the reinforcement of the Hadejia 132/33KV substation with an additional 60 MVA power transformer as part of efforts to improve power supply in Nigeria.
The Transmission Company of Nigeria (TCN) has, for the first time in the last 20years, maintained grid frequency stability within the operating band of 49.5Hz to 50.5Hz for 24 consecutive hours. This important milestone, which was achieved on the 14th of June, 2017, is a key pointer to the gradual and consistent improvement in the stability of the nation’s transmission grid.
Sequel to Government directives on the above, a draft Application Procedure for connecting New and Modified Users to the TCN Transmission grid has been developed and sent to NERC for approval before it would be posted on this site. Both the Application Procedure and Application form shall be uploaded, the Application form could be down-loaded, filled and submitted with a non-refundable processing fee of N200,000.00 only.
The Interim Managing Director of the Transmission Company of Nigeria, TCN, Mr. Usman Gur Mohammed, has commended the Managements of Power Generating Companies for deploying Free Governor Control mechanisms in their power plants which have resulted in improved grid stability and reliability.